S. No.
|
NATURE OF POWER
|
|
DELEGATION
|
|
|
|
|
|
|
1
|
Sanction of Capital works
|
Rs. 5 lac
|
AMD
|
Subject to
Budget provision
& clearance
finance
|
|
|
|
|
|
2.
|
(a) To decide rates of items
work not available in PWD
Common Schedule of rates
|
Full Powers
|
CM Engg.
|
|
|
(b) To decide the rate of items
of works which are neither
given in common schedule
of rates of PWD nor in
the arrangement.
|
Full Powers
|
CM Engg.
|
|
|
|
|
|
|
3
|
(a) Execution of the contract
in r/o of Sanction works and
approved tenders
|
Full Powers
|
CM Engg.
|
|
|
(b) Signing of agreements on
behalf of MD, after tenders
are finally approved by
competent authority
|
Full Powers
|
CM Engg.
|
|
|
|
|
|
|
4
|
Execution of time limit of
contracts.
|
Full Powers in
respect of contract
awarded within his
competence provided
the execution granted
does not exceed 1/5
of time stipulated in
the contract agreement
|
CM Engg.
|
|
|
|
|
|
|
5
|
To purchase construction
material with tenders
|
|
|
|
|
(a) On rate contract
|
Full Powers
|
CM Engg.
|
In consultation
with Finance.
|
|
(b) Open market after ceiling
quotation in emergent cases on
recommendation of CM Engg.
|
Upto Rs. 15000/-
Exceeding Rs. 15000/-
|
Purchase
Purchase
committee of CM
Engg. SDO &
AMD or his Rep.
|
In consultation
with Finance.
-do-
|
|
(c) On control price against
allocation by Govt.
|
Full Powers
|
CM Engg.
|
|
|
|
|
|
|
6.
|
Sale of Surplus store
|
Up to Rs. 5lac by
tenders
|
CM Engg.
|
In Consultation
with finance
|
|
|
|
|
|
7.
|
Technical Section
|
Up to Rs. 10000/-
Full Powers
|
SDO
CM Engg.
|
|
|
|
|
|
|
8.
|
(a) To incur expenditure on
office contingencies
|
Rs. 1000/-
|
SDO
|
Subject to
Rs.5000/-pa
|
|
|
Rs. 5000/-
|
CM Engg.
|
Subject to
Rs.25000/pa
|
|
(b) To incur expenditure on
contingencies
|
Rs.2000/-
|
SDO
|
Subject to
Rs. 1000/-pa
|
|
(c) Hiring of equipment transport
& other tools and plants for
execution of works departmentally
|
Upto Rs.25000/-for
each item at one time.
|
CM Engg.
|
In consultation
with finance
|
|
|
|
|
|
9.
|
To levy compensation /penalty
on contractors in case of :-
a) Delay
b) Dad work
|
Full Powers
Full powers
|
CM Engg.
CM Engg.
|
|
|
|
|
|
|
10.
|
To create post of Work charged
|
Full Power Subject to
provision in the estimate
|
CM Engg.
|
|
|
|
|
|
|
11.
|
To sanction repair & carriage
of T&P and construction material
|
Full Powers
|
CM Engg.
|
In Consultation
with finance
|
|
|
|
|
|
12
|
Passing of bills of construction/
repair of godowns/plinths etc
|
Full Powers
|
CM Engg.
|
|
|
|
|
|
|
13
|
Payments against bills of
construction/ repairs of godowns
plinths etc
|
Full Powers
|
CM (F&A)
|
As per delegation
of powers relating
to operation of
bank accounts.
|